The eBusiness suite server and operating system (O/S) extended support ends in 2020. This database upgrade is needed to manage the risk of end of life technology. It is proposed that this work takes place in 18/19 to minimise the impact to business areas that will be impacted by core systems implementation from 2019 onwards.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2018 BLUE 40.0 days 39.9 days 0.0

Project Info

Project
eBusiness Suite - Database Update
Code
PPP013
Programme
Z. Payroll and Pensions (PPP) (closed)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Pamela Baillie
Current Stage
Close
Status
Closed
Start Date
24-Aug-2018
Planning Date
21-Sep-2018
Delivery Date
30-Oct-2018
Close Date
30-Nov-2018
Overall Priority
Normal

Project Dashboard

Project journal

No entries found.