Q3 2017-18

Report Date
May 2018

Have surpassed 400k in cash savings (yearly target was 350k, has been upped to 400k) with reuse continuing to be positive. PC reuse role has been filled with Bradley continuing in post till end of 2018 calendar year. Lab progress being made with promotion of flow chart to follow  in Q4 to help drive reuse in this area. 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
REF2 Expanding Reuse at University of Edinburgh
Code
REF2
Programme
SRS - Resource Efficiency (REF) and Circular Economy
Project Manager
Alan Peddie
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
01-Aug-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2021
Overall Priority
Normal

Documentation

Not available.