Progress Update for w/c 15 Oct 2012

1 remaining JIRA call for Non R Codes to be tested and signed off.  This has been delayed due to problems on BETA with running the extract.  Dev Tech and Config Team currently resolving.

Dev Tech also progressing the DR configuration as a result of the discussions with Atira relating to the application server data storage.

Project Info

Project
Implementation of PURE Publications Service
Code
RES037
Programme
Z. Research (RES) (closed August 2017)
Project Manager
Adam Wadee
Project Sponsor
Nigel Brown
Current Stage
Close
Status
Closed
Start Date
01-Mar-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
26-Jul-2013
Overall Priority
Normal
Category
Discretionary