Report for May 2013

Report Date
May 2013

Achievements in Last Period

  • DR testing completed by Dev Tech and Tech Man.
  • The Non R Code extract has gone live, and Config Team are resolving the post-go live JIRA calls.  GaSP and IS Apps met to clarify the JIRA calls that need to be resolved before the project can close.  The following JIRAs are in progress and will be resolved under RES037:

    RES037-262 - action on GaSP/College Accountants RES037-279 - action on Config Team / RGS RES037-289 - action on RGS / GaSP RES037-293 - action on Config Team RES037-283 - action on Config Team

  • It has been agreed to resolve the lower priority JIRA calls in the RES049 Pure Enhacements project.

 

Issues

  • The milestones have been revised.

Next Steps

  • Close project

 

Target dateTitle
21-Jun-2013DSOR
12-Jul-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Implementation of PURE Publications Service
Code
RES037
Programme
Z. Research (RES) (closed August 2017)
Project Manager
Adam Wadee
Project Sponsor
Nigel Brown
Current Stage
Close
Status
Closed
Start Date
01-Mar-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
26-Jul-2013
Overall Priority
Normal
Category
Discretionary