Live deployment successfully completed

Issues encountered with the Live deployment were resolved by close of Friday 14th Dec.

The Test deployment could not be completed last week, because the HR system was unavailable as it was being re-cloned from Live.

When HR Test becomes available following the completion of the cloning process, the deployment issues will also be resolved in Test.

Project Info

Project
PURE HR Changes for REF
Code
RES043
Programme
Z. Research (RES) (closed August 2017)
Project Manager
Jill Nicoll
Project Sponsor
Alexis Cornish
Current Stage
Close
Status
Closed
Start Date
15-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Feb-2013
Overall Priority
Normal
Category
Compliance