PURE projects review - 10th December 2012
Present: Defeng Ma, Alyson Shaw, Clive Davenhall, Greg Fleming, Jill Nicoll Apologies: Adam Wadee
Meeting Note:
RES043 – HR extract
Current Status:
- UAT signed off in Beta
Next Steps:
- Neil to deploy to Test tomorrow (Tuesday)
- Manya to re-test the day following the Test deployment
- Go-live to be coordinated with the Live release of PURE 4.14.2 (due to dependency on new FTC field)
- No down-time or at-risk announcement is required for the HR extract deployment, as this is a nightly scheduled task
RES037 – Non-R Code
Current Status:
- Jira RES037-241 – Data issue
- Jira RES037-254 – Clive has worked out a fix, but this is on hold pending RES043 progress
- Jira RES037-259 – Clive has worked out a fix, but this is on hold pending RES043 progress
- Jira RES037-266 – “Missing Person” code, Clive has some concerns, and would like to talk these through with Alyson
Next Steps:
- Jira RES037-241 – to be returned to Manya
- Jiras RES037-254 and RES037-259 – to be taken forward together, from today, to form the next release
- Jira RES037-266 – to be confirmed – see below
Jira RES037-266 – “Missing Person” code
Work on this Jira will be suspended pending the deployment of fixes for Jiras RES037-254 and RES037-259
Options:
- Keep RES043 open and transfer Jira RES037-266 to the RES043 Jira log.
- Go ahead with RES043 closure, but transfer any remaining days from RES043 to RES037, to cover the effort needed for RES037-266
Following the meeting, Jill and Adam discussed the options and agreed that RES043 would close in early January following the post-deployment support period. Any days remaining in RES043 will then return either to the RES programme or directly to RES037, to be used for the further investigation of RES037-266.