Organisation

 

Work/Task Breakdown

System Design Specification - System Designer

Code changes - Developer

Peer testing - System Designer

Address peer testing feedback - Developer

Deploy to Test - Dev Tech analyst

UAT Test - GaSP manager

Address UAT testing feedback - Developer

Deploy to Test - Dev Tech analyst

UAT re-testing and sign-off - GaSP manager

Deploy to Live - Dev Tech analyst

Post-deployment support - System Designer & Developer

 

Resources Skills and Cost

 

IS Apps SectionTeam Estimate (Days)
Project Services Project Services 8.0
Development ServicesConfiguration Team 22.2
 Development Technology 1.8
Directors OfficeDirectors Office1.0
 Total Days33.0

 

Project Info

Project
PURE HR Changes for REF
Code
RES043
Programme
Z. Research (RES) (closed August 2017)
Project Manager
Jill Nicoll
Project Sponsor
Alexis Cornish
Current Stage
Close
Status
Closed
Start Date
15-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Feb-2013
Overall Priority
Normal
Category
Compliance