Report for October 2012

Report Date
October 2012

Achievements in Last Period:

Project Proposal submitted

Business Requirements identified

System Design completed

System enhancements coded

Issues

The project's proposal estimate of 15 days has already been exceeded.  This is due to:

  • Additional effort required for skill transfer to, and learning curve of, a new Configuration Team resource assigned to code the system enhancements. 
  • Scope added to resolve an issue identified in code that had previously been released for UAT testing.
  • Scope added to investigate warning messages from the Person sync. 

The System Designer's project booking was lost to the HR system's R12 upgrade project.  As a result:

  • The Project Brief has been delayed, as the Designer''s input is required for the revised estimates. 
  • The release for UAT testing has been delayed, as the Designer is required for the peer testing.

Late in October, the project management was transferred from Adam Wadee to Jill Nicoll. 

The Business Manager has indicated that she may change the business requirements for the project's largest item.  If these requirements do change, then the budget will have to be further increased, first to remove the code changes that have already been completed, and then to code the new changes.

Next Steps:

Business Manager to confirm business requirements

ISA team to

  • Complete Project Brief
  • Complete Peer Testing
  • Release for UAT Testing

 

Project Status
RAG Status
Time
AMBER
Cost
RED
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
15.0 days
Activity this month
17.0 days
Activity this year
18.0 days
Activity to date
18.0 days
Estimate to complete current year
16.0 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE HR Changes for REF
Code
RES043
Programme
Z. Research (RES) (closed August 2017)
Project Manager
Jill Nicoll
Project Sponsor
Alexis Cornish
Current Stage
Close
Status
Closed
Start Date
15-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Feb-2013
Overall Priority
Normal
Category
Compliance