Report for November 2012
- Report Date
- November 2012
Achievements in Last Period:
Changes to requirements coded, peer tested, and released for UAT in the Beta environment
Issues
Revised requirements, and the continuing unavailability of the Lead Developer, led to a delay in completing the build and releasing it for UAT testing in the Beta enviroment.
The Business Area Manager has indicated that another requirement may be revised. If confirmed, this requirement change would have to be estimated, and additional resources requested to complete it. However, the project's Lead Developer is available only until 11th December. After this date, she will be fully committed to a Priority 1 legislative project until February 2013.
Next Steps:
UAT testing and sign-off in Beta environment
Implementation Plan
Implementation to Test environment
UAT re-testing and sign-off in Test environment
Milestones:
12-Dec-2012 | Acceptance Sign-off |
11-Jan-2013 | Deployment Sign-off |
23-Jan-2013 | Closure |
- Approved budget
- 33.0 days
- Activity this month
- 6.2 days
- Activity this year
- 24.6 days
- Activity to date
- 24.6 days
- Estimate to complete current year
- 8.2 days
- Estimate to complete future years
- 0.0 days