Report for November 2012

Report Date
November 2012

Achievements in Last Period:

Changes to requirements coded, peer tested, and released for UAT in the Beta environment

Issues

Revised requirements, and the continuing unavailability of the Lead Developer, led to a delay in completing the build and releasing it for UAT testing in the Beta enviroment. 

The Business Area Manager has indicated that another requirement may be revised.  If confirmed, this requirement change would have to be estimated, and additional resources requested to complete it.  However, the project's Lead Developer is available only until 11th December.  After this date, she will be fully committed to a Priority 1 legislative project until February 2013. 

Next Steps:

UAT testing and sign-off in Beta environment

Implementation Plan

Implementation to Test environment

UAT re-testing and sign-off in Test environment

  

 Milestones

12-Dec-2012

Acceptance Sign-off
11-Jan-2013Deployment Sign-off
23-Jan-2013Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
AMBER
Overall
GREEN
Change Status
Activity
Approved budget
33.0 days
Activity this month
6.2 days
Activity this year
24.6 days
Activity to date
24.6 days
Estimate to complete current year
8.2 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE HR Changes for REF
Code
RES043
Programme
Z. Research (RES) (closed August 2017)
Project Manager
Jill Nicoll
Project Sponsor
Alexis Cornish
Current Stage
Close
Status
Closed
Start Date
15-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Feb-2013
Overall Priority
Normal
Category
Compliance