Report for December 2012 and January 2013
- Report Date
- January 2013
Achievements in Last Period:
- UAT testing and sign-off in Beta environment
- Implementation Plan
- Implementation to Test environment
- UAT re-testing and sign-off in Test environment
- Deployment to Live
- Live Deployment sign-off
- Completion Report
- Closure approved by Business Area Manager
Issues
n/a
Next Steps:
Awaiting closure sign-off confirmation from HR stakeholder
- Approved budget
- 33.0 days
- Activity this month
- 7.0 days
- Activity this year
- 31.5 days
- Activity to date
- 31.5 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days