December 2014
- Report Date
- December 2014
Achievements in last period
- Build continues
Issues
- Need to ensure that the work packages in the sprints do not affect the PURE feed.Review to be carried out.
Next StepsĀ
- Build continues
- Build to complete at end of January.
- Approved budget
- 95.0 days
- Activity this month
- 10.0 days
- Activity this year
- 35.0 days
- Activity to date
- 60.0 days
- Estimate to complete current year
- 40.0 days
- Estimate to complete future years
- 0.0 days