- Report Date
- January 2015
Achievements in last period
Issues
- Emering issue with scheduling of PURE upgrades, new project model and PGR project, in discussion with Business Lead. Project at Amber because of this.
Next StepsĀ
- Build continues
- Agree solution of scheduling PURE activity, which will re-set milestones and estimate
- Approved budget
- 95.0 days
- Activity this month
- 10.0 days
- Activity this year
- 45.0 days
- Activity to date
- 70.0 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 0.0 days