February 2015

Report Date
February 2015

Achievements in last period

  • Developer has tidied up what build has been completed so far and carried out analysis of the eFIN to PURE feed.

Issues

  • Scheduling and resourcing issue PURE upgrades, new project model and PGR project, in discussion with Business Lead. Project at Amber because of this. Solution being proposed to PURE Business Lead and Project Board for approval.
  • Lead Developer is leaving the company mid-April, therefore a replacement Developer is also required.

Next Steps 

  • Put forward proposal for approval
  • Re-set milestones and estimate once agreed
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
95.0 days
Activity this month
4.0 days
Activity this year
74.0 days
Activity to date
74.0 days
Estimate to complete current year
38.0 days
Estimate to complete future years
0.0 days

Project Info

Project
RMAS Worktribe - PURE Integration
Code
RES057
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Build
Status
Withdrawn
Start Date
27-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
2
Overall Priority
Normal
Category
Compliance