March 2015
- Report Date
- March 2015
Achievements in last period
- Developer has tidied up what build has been completed so far and carried out analysis of the eFIN to PURE feed.
- Meetings with stakeholders to discuss potential for delaying the implementation of the PURE feed until after RMAS has gone live.
Issues
- Re-estimate to be signed off by the RMAS Project Board. Costings given below are approximate, to be confirmed.
Next Steps
- Put forward proposal for approval by the Project Board on 7 April.
- Arrange project closure.
Milestones
07-Apr-2015 | Revised Scope, Plan and Costings Signed Off by Project Sponsor |
24-Apr-2015 | Handover of Development to-date |
- Approved budget
- 95.0 days
- Activity this month
- 1.0 day
- Activity this year
- 50.0 days
- Activity to date
- 76.0 days
- Estimate to complete current year
- 7.0 days
- Estimate to complete future years
- 82.0 days