Report for July 2015
- Report Date
- July 2015
Project Suspended, while focus is on the Pilot and full roll-out of Worktribe for Research grant costings and approval
Estimate to complete build and deploy to LIVE is a further 75 days effort
Hugh Edmiston ( Project sponsor and Director of Corporate Services ) has asked for a contribution of 25 days from each of the College ring-fenced IS Apps budgets for 15-16 to complete this project. This request has gone via the College Registrars to CHSS< CSCE and CMVM
- Approved budget
- 95.0 days
- Activity this month
- 0.0 days
- Activity this year
- 53.0 days
- Activity to date
- 78.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 75.0 days