Report for July 2015

Report Date
July 2015

Project Suspended, while focus is on the Pilot and full roll-out of Worktribe for Research grant costings and approval

Estimate to complete build and deploy to LIVE is a further 75 days effort

Hugh Edmiston ( Project sponsor and Director of Corporate Services ) has asked for a contribution of 25 days from each of the College ring-fenced IS Apps budgets for 15-16 to complete this project. This request has gone via the College Registrars to CHSS< CSCE and CMVM

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
95.0 days
Activity this month
0.0 days
Activity this year
53.0 days
Activity to date
78.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
75.0 days

Project Info

Project
RMAS Worktribe - PURE Integration
Code
RES057
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Build
Status
Withdrawn
Start Date
27-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
2
Overall Priority
Normal
Category
Compliance