Report for May 2017
- Report Date
- May 2017
Achievements in Last Period
- None - Project suspended
Issues
- None - Project suspended
Next Steps
- Project has been Suspended since April 2015 while business focus has been on full roll-out and then embedding the new Worktribe Research Management system
- Estimate to complete build and deploy to LIVE has been re-estimated at 100d - as several key developers have left the University since the project was suspended
- The 100d to complete this project has been allocated as a compliance project in the 2017-18 financial year for the RES programme
- This project can't be delivered until PURE has moved to the new Project Model (or otherwise the system design for this feed would need to be altered - the design was done in relation to the new Project model in PURE)
- The system design will need to re-visited when this project is re-started - as both Worktribe and PURE have moved to new versions since the initial design and build was started.
- This project should also engage with the Enterprise Architecture team , as new standards for data feeds and APIs are being developed , to be used for all new integration projects
- Approved budget
- 178.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 78.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 100.0 days