Report for March 2014
- Report Date
- March 2014
Achievements in last period
- Business requirements finalised
Issues
- None
Next Steps
- Sign off project brief
- Sign off business requirements
Target date | Title |
14-Mar-2014 | Brief Signed Off |
11-Apr-2014 | Business Requirements Signed Off |
30-May-2014 | Business Requirements Signed Off (with Supplier) |
27-Jun-2014 | System Design Complete |
29-Aug-2014 | Build Complete |
26-Sep-2014 | Integration Test Signed Off |
10-Oct-2014 | Project Close |
- Approved budget
- 35.0 days
- Activity this month
- 0.6 days
- Activity this year
- 2.0 days
- Activity to date
- 2.0 days
- Estimate to complete current year
- 22.0 days
- Estimate to complete future years
- 11.0 days