June 2014

Report Date
June 2014

Achievements in last period

  • Business requirements signed off
  • Design underway

Issues

  • Could be some dependencies on the other RMAS work streams

Next Steps 

  •  Complete SDS and arrange sign off 

 

 

Target dateTitle
01-Aug-2014System Design Complete
26-Sep-2014Build Complete
10-Oct-2014Integration Test Signed Off
24-Oct-2014Project Close

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
45.0 days
Activity this month
12.0 days
Activity this year
17.0 days
Activity to date
17.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
26.0 days

Project Info

Project
RMAS Worktribe - PURE Integration
Code
RES057
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Build
Status
Withdrawn
Start Date
27-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
2
Overall Priority
Normal
Category
Compliance