August 2014

Report Date
August 2014

Achievements in last period

  • SDS Reviewed
  • Re-estimate completed

Issues

  • Project in the process of being re-estimated along with parent project, RES051

Next Steps 

  • Updated SDS to be issued for sign off
Project Status
RAG Status
Time
RED
Cost
RED
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
45.0 days
Activity this month
7.5 days
Activity this year
7.5 days
Activity to date
25.5 days
Estimate to complete current year
19.5 days
Estimate to complete future years
19.5 days

Project Info

Project
RMAS Worktribe - PURE Integration
Code
RES057
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Build
Status
Withdrawn
Start Date
27-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
2
Overall Priority
Normal
Category
Compliance