Project Update - 14th June 2017

Phase 1 was delivered in Nov 2016

Phase 2 fixes were deployed into TEST in April 2017 , and are with the IS L&UC Research Support team to test.

The intention is to close RES060 , once the Phase 2 UAT is complete , and once the Phase 2 changes have been promoted to LIVE

--

A new issue was reported today by Stuart Craig in Production Management who has noticed that some PGR students who have a supervisor who is a current visitor - are incorrectly being recorded as errors and the Supervisor is being dropped , as there is in-correct validation rule that works OK for permanent UoE staff on HR, but doesn't work for visiting staff who have no HR ID , but a Visitor ID instead.

This will require a change to the validation rule to be applied to DEV and TEST , then the change will need to pass testing by the IS L&UC Research support team - before it can be promoted to LIVE.

Once this issue in LIVE is resolved, and once Phase 2 is correctly deployed to LIVE - then RES060 can close

Project Info

Project
PGR Feed to PURE
Code
RES060
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Kevin Brennan
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
23-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Sep-2017
Programme Priority
3
Overall Priority
Normal
Category
Compliance