RES062: PURE Upgrade to Oracle 12c Status Report - DRAFT

Report Date
April 2016

Achievements this period

Initial meetings set up with Jill Nicoll, Mark Lang and James Toon to introduce myself and discuss initial RES062: PURE Upgrade to Oracle 12c expectations and dependencies between PURE upgrade and Oracle 11g-12c.

The previous PURE migration to Oracle 11g was approx 2 years ago. Whilst Oracle 12c tech is slightly different the process can potentially be cut and paste.

Similarly worst/likely/best time estimates will be similar, however, downtime has been reduced to approx 1hr.

Gillian Henderson has been identified as Dev Tech Lead 

Issues

NONE

Next Steps

Complete Planning

Complete 3Point Estimate

Commence Business Analysis

Milestones

Target date

Previous Date

Title

Complete

20/05/16

20/05/16

Planning

NO

17/10/16

17/10/16

Delivery

NO

16/12/16

16/12/16

Closure

NO

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
45.0 days
Activity this month
1.3 days
Activity this year
1.4 days
Activity to date
1.4 days
Estimate to complete current year
36.4 days
Estimate to complete future years
8.4 days

Project Info

Project
PURE Upgrade to Oracle 12c
Code
RES062
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Dec-2017
Programme Priority
2
Overall Priority
Normal
Category
Compliance