Report for August 2017

Report Date
August 2017

Achievements in Last Period

  • DEV and TEST data is now refreshed from LIVE
  • Milestones replaned
  • Risks reviewed and removed / added as necessary
  • Patch update to PURE not required. There is a patch update required to Oracle 12, but is included in 12.2. As we are moving to 12.2, there is no need to patch Oracle either.

Issues

  • Delay in starting the refresh of data as the annual rollover of Finance data had to be completed before backups could be taken from PURE LIVE.
  • Cost has put the project into AMBER as 10 days were originally allocated to the project for 17/18, but due to delays in 16/17 in getting resource the anticipated work was not carried out and been moved into the 17/18 year. A further¬† 16 days are required for this project.

 

Next Steps

  • Review previous project activity, ie the TAD and the plan are up to date.
  • ¬†
  • begin the migration to DEV
  • Integration testing
  • Acceptance testing

Milestones

15-Sep-2017 Build
20-Sep-2017 Integration
27-Sep-2017 Acceptance
05-Oct-2017 DELIVERY
30-Nov-2017 CLOSURE
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
10.0 days
Activity this month
3.0 days
Activity this year
2.0 days
Activity to date
24.0 days
Estimate to complete current year
26.0 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE Upgrade to Oracle 12c
Code
RES062
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Dec-2017
Programme Priority
2
Overall Priority
Normal
Category
Compliance