Report for September

Report Date
September 2017

Achievements in Last Period

  • Dev migration completed, tested and signed off.
  • Preparation for the migration to TEST.

Issues

  • Timeline has slipped a couple of weeks due to annual leave in September, however will not impact the closure date.

 

Next Steps

  • Migrate to TEST
  • Integration testing
  • UAT

Milestones

13-Oct-2017 Integration
20-Oct-2017 Acceptance
31-Oct-2017 DELIVERY
30-Nov-2017 CLOSURE
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
25.0 days
Activity this month
20.0 days
Activity this year
27.0 days
Activity to date
49.0 days
Estimate to complete current year
18.0 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE Upgrade to Oracle 12c
Code
RES062
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Dec-2017
Programme Priority
2
Overall Priority
Normal
Category
Compliance