Report for October 2017

Report Date
October 2017

Achievements in Last Period

  • Migrate to TEST achieved
  • Integration testing passed.
  • UAT passed
  • Deployment to LIVE achieved
  • Budget change approved

 

Issues

  • None

 

Next Steps

  • Deployment sign off review
  • Closure report write-up and distribute for review
  • Project closure

Milestones

14-Nov-2017 Deployment sign off review
30-Nov-2017 CLOSURE
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
45.0 days
Activity this month
17.0 days
Activity this year
44.0 days
Activity to date
66.0 days
Estimate to complete current year
2.5 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE Upgrade to Oracle 12c
Code
RES062
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Dec-2017
Programme Priority
2
Overall Priority
Normal
Category
Compliance