Report for November 2017
- Report Date
- November 2017
Achievements in Last Period
- Deployment sign off review achieved
- Closure report written and distributed
- All closure signoffs received with the exception of Apps Man due to annual leave.
Issues
- Closure delayed due to annual leave of Applications Management representative required for sign off. Closure will be achieved by 08/12/2017 as this has now been signed off and submitted to WIS.
Next Steps
- Project closure approval
Milestones
30-Nov-2017 | CLOSURE |
- Approved budget
- 45.0 days
- Activity this month
- 1.4 days
- Activity this year
- 46.0 days
- Activity to date
- 68.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days