PURE Upgrade to Oracle 12c

Report Date
May 2016

Achievements this period

Planning complete/ Project Brief Signed Off/WIS SIgn Off

3Point Estimate completed/ Resource secured in principle

Business Requirements drafted based on SAS001

Issues

PURE upgrade to Oracle 12c within 15/16 is no longer possible

https://www.projects.ed.ac.uk/project/res062/issues/2

Next Steps

Draft Business Requirements Document

BRD Sign Off

Draft Technical and System design documents/UAT implementation/ Test scripts etc where ever possible

Address WIS comments 27/05

Pending Decisions

Implement the backlog of patches prior to migrating PURE to 12c. Approx duration 8 weeks. Based on whether the current version of PURE (5.4.2) is supported or 

Implement v5.7 before migrating PURE to 12c as current version 5.4.2 is not supported but no further patches or

Holdback all patches until PURE has been migrated to 12c and then implement

Dependancies

Business desire to deliver with 15/16                                      Wiki and JIRA having been migrated to 12c first

RES60 successfully completing TEST phase                        Change Freeze

Available resource

Milestones

Target date

Title

Complete

27/05/16

Planning

YES

14/11/16

Delivery

NO

13/01/17

Closure

NO

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
45.0 days
Activity this month
4.5 days
Activity this year
7.1 days
Activity to date
7.1 days
Estimate to complete current year
13.6 days
Estimate to complete future years
23.9 days

Project Info

Project
PURE Upgrade to Oracle 12c
Code
RES062
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Dec-2017
Programme Priority
2
Overall Priority
Normal
Category
Compliance