June 2016 draft

Report Date
June 2016

Achievements this period

Business Requirements Document signed off

Background tasks established and recorded on ASTA/Plan

WIS comments addressed

Established patch required for 5.4.2 to be supported by 12c

Issues

PURE upgrade to Oracle 12c within 15/16 is no longer possible

https://www.projects.ed.ac.uk/project/res062/issues/2

Next Steps

Pending Decisions

Implement the backlog of patches prior to migrating PURE to 12c. Approx duration 8 weeks or 

Holdback all patches until PURE has been migrated to 12c and then implement

Dependancies

Wiki and JIRA having been migrated to 12c first                  

RES60 successfully completing TEST phase                        

Implementing v5.6 (with/without 12c supporting patch)

Change Freeze                                                                            

Available resource                                                                      

Milestones

Target date

Title

Complete

27/05/16

Planning

YES

14/11/16

Delivery

NO

13/01/17

Closure

NO

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
45.0 days
Activity this month
5.0 days
Activity this year
12.2 days
Activity to date
7.1 days
Estimate to complete current year
5.1 days
Estimate to complete future years
27.7 days

Project Info

Project
PURE Upgrade to Oracle 12c
Code
RES062
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Dec-2017
Programme Priority
2
Overall Priority
Normal
Category
Compliance