RES062: PURE Upgrade to Oracle 12c Status Report as@ 27/07/16

Report Date
July 2016

Achievements this period

Background tasks undertaken:

  • Update TAD/Investigate CMDB entry
  • Build record 12c migration/Update migration including interface steps
  • Environment - associated firewalls/Create accounts

Issues

PURE upgrade to Oracle 12c within 15/16 is no longer possible

https://www.projects.ed.ac.uk/project/res062/issues/2

Dependancies

Wiki and JIRA having been migrated to 12c first                  

RES60 successfully completing TEST phase                        

Implementing v5.6 (with/without 12c supporting patch)

Change Freeze                                                                            

Available resource

Next Steps

Project suspension ( Approved for 2 months) 

https://www.projects.ed.ac.uk/project/res062/issues/6     

Approved at WIS 

https://www.wiki.ed.ac.uk/display/insite/Applications+WIS+Notes+-+29+July+2016

 

 

 

                                             

Milestones - post suspension

Target date

Title

Complete

27/05/16

Planning

YES

24/01/17 (14/11/16)

Delivery

NO

27/03/17 (13/01/17)

Closure

NO

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
45.0 days
Activity this month
3.0 days
Activity this year
15.6 days
Activity to date
15.6 days
Estimate to complete current year
0.0 days
Estimate to complete future years
29.0 days

Project Info

Project
PURE Upgrade to Oracle 12c
Code
RES062
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Dec-2017
Programme Priority
2
Overall Priority
Normal
Category
Compliance