Report for Nov 2016

Report Date
November 2016

Achievements this period

None - Project still suspended

 

Issues

None

 

Dependancies

RES60 Phase 1 successfully deployed to LIVE ( DONE - 9-Nov 2016) 

Wiki and JIRA having been migrated to 12c first                  

Implementing v5.6 (with/without 12c supporting patch)

Scheduling around the project to replace the PURE App tier                                                                   

Available resource in IS Apps Dev tech

Next Steps

Project to re-start in Feb 2017 ( project suspension extended)  

Original project suspension approved at WIS 

https://www.wiki.ed.ac.uk/display/insite/Applications+WIS+Notes+-+29+July+2016

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
29.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
16.0 days
Estimate to complete current year
29.0 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE Upgrade to Oracle 12c
Code
RES062
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Dec-2017
Programme Priority
2
Overall Priority
Normal
Category
Compliance