This project has been initiated to complete Worktribe Upgrade to v2.3. The upgrade to this version is also required to accommodate the Apprenticeship Levy (0.5%) which started in April 2017, this is currently being absorbed by the University as the payroll system has not been updated to account for the levy introduction. This will change in August when the levy will be passed onto schools. The change for the Apprentice Levy is being back ported in Worktribe v2.3 therefore the upgrade is required to provide this necessary change.

 

(AP67-952)

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2017 GREEN 50.0 days 11.6 days 39.0

Project Info

Project
Worktribe Upgrade v2.3 & Apprenticeship Levy
Code
RES070
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Ben Armstrong
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
26-May-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Aug-2017
Overall Priority
Normal
Category
Discretionary

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.