Report for May 2020

Report Date
May 2020

Achievements in Last Period 

  • Project closure completed and approved

Issues

  • None

Next Steps

  • None

The project status is CLOSED

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
60.0 days
Activity this month
0.0 days
Activity this year
1.7 days
Activity to date
60.9 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Ethics Tool Procurement
Code
RIS005
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Lorna Thomson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
28-Feb-2020
Planning Date
20-Mar-2020
Delivery Date
15-May-2020
Close Date
15-May-2020
Overall Priority
Normal
Category
Discretionary