GoCAB need confirmation when Test completes on both 5.13 and 5.15

Change C1907-017 - - RIS007 - Pure v5.13 Upgrade on Live

GoCAB (unidesk@ed.ac.uk) require confirmation 5.13 Test is complete with all data checks before 6 August to approve outage on 8 August for 5.13 Live. The same for 5.15 before 31 October. See actions for both Live milestones (5.14 upgrades assumed not proceeding at time of writing (9 July 2019)).

Project Info

Project
PURE Upgrades v5.13 to v5.15
Code
RIS007
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Nov-2018
Planning Date
31-Jan-2019
Delivery Date
19-Nov-2019
Close Date
10-Dec-2019
Programme Priority
4
Overall Priority
Higher
Category
Compliance