Report for July 2019

Report Date
July 2019

Achievements in Last Period

  • 5.13 TEST Tomcat upgrade, refresh and upgrade completed 9 July
  • UAT completed and signed off by business team
  • Preparation activity for live deployment - Go CAB, Service Alert and communication to users

Issues

  • Revised milestone for Live deployment to 8th August
  • Descoped GDPR activity
  • Reduction of budget for descope work and additional deployment agreed and approved

Next Steps 

  • 5.13.4 Live Tomcat upgrade scheduled for 8th August
  • Commence prep work for Cloud portal
  • Data refresh for Dev and Test from Live
  • Commence Java Upgrade in Dev and Pure 5.15.1 upgrade for Dev

 

The project status is GREEN 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
Activity
Approved budget
115.0 days
Activity this month
11.5 days
Activity this year
46.3 days
Activity to date
46.3 days
Estimate to complete current year
2.7 days
Estimate to complete future years
66.0 days

Project Info

Project
PURE Upgrades v5.13 to v5.15
Code
RIS007
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Nov-2018
Planning Date
31-Jan-2019
Delivery Date
19-Nov-2019
Close Date
10-Dec-2019
Programme Priority
4
Overall Priority
Higher
Category
Compliance

Documentation