Report for August 2019

Report Date
August 2019

Achievements in Last Period 

  • Pure 5.13.4 Live upgrade and Tomcat upgrade completed successful on 8th August
  • Commenced prep work for Cloud portal
  • Data refresh for Dev and Test completed from Live for next upgrade activity
  • ROS Tables removed from Dev, Test and Live
  • Java Upgrade and Pure 5.15.1 upgrade completed for Dev

Issues

  • Deployment of 5.15.1 allows the RIS team to prep training with business users however as expected some issues encountered and not suitable for this version to be taken through test to live.
  • Key issues is rendering of UI
  • Revise dates for delivery to Test and Live dependent on availability of 5.12.2 code from Elsevier
  • Submit revised milestones to WIS for approval

Next Steps 

  • Upgrade Dev environment to Pure 5.15.2
  • Upgrade Test environment to Pure 5.15.2 and Java Upgrade
  • Commence UAT
  • Prep for Cloud Portal

 

The project status is GREEN 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
Activity
Approved budget
115.0 days
Activity this month
0.0 days
Activity this year
46.3 days
Activity to date
46.3 days
Estimate to complete current year
66.0 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE Upgrades v5.13 to v5.15
Code
RIS007
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Nov-2018
Planning Date
31-Jan-2019
Delivery Date
19-Nov-2019
Close Date
10-Dec-2019
Programme Priority
4
Overall Priority
Higher
Category
Compliance

Documentation