Report for September 2019

Report Date
September 2019

Achievements in Last Period 

  • Upgrade Dev environment to Pure 5.15.2
  • Upgrade Test environment to Pure 5.15.2-1 and Java Upgrade
  • Commenced UAT within Business teams for 6 weeks
  • Prep for Cloud Portal

Issues

  • Due to delay in receiving 5.15.2-1 release project is 2 weeks behind schedule 
  • Business team require 6 weeks to complete UAT and tidy data
  • Revised milestones for remaining activity completed, resulting in Live deployment of Java and pure 5.15.2-1 now 19th November 2019
  • Review budget as activity is reduced

Next Steps 

  • Upgrade Dev environment to Pure 5.15.2
  • Upgrade Test environment to Pure 5.15.2 and Java Upgrade
  • Commence UAT
  • Prep for Cloud Portal - schedule meeting with Elsevier end of October / early November

 

The project status is GREEN 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
Revised Milestones approved due to 2 week delay from supplier
Activity
Approved budget
115.0 days
Activity this month
3.2 days
Activity this year
14.6 days
Activity to date
64.5 days
Estimate to complete current year
27.4 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE Upgrades v5.13 to v5.15
Code
RIS007
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Nov-2018
Planning Date
31-Jan-2019
Delivery Date
19-Nov-2019
Close Date
10-Dec-2019
Programme Priority
4
Overall Priority
Higher
Category
Compliance

Documentation