Report for November 2018

Report Date
November 2018
Achievements to date
  • Project Brief has been drafted

Issues

There is one issue to report at this stage:

PICCL 1: End of Planning Milestone not achieved

Next Steps 
  • Project brief approved
  • Project plan revised accordingly
  • Project Team established
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Activity
Approved budget
150.0 days
Activity this month
0.3 days
Activity this year
0.3 days
Activity to date
0.3 days
Estimate to complete current year
78.6 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE Upgrades v5.13 to v5.15
Code
RIS007
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Nov-2018
Planning Date
31-Jan-2019
Delivery Date
19-Nov-2019
Close Date
10-Dec-2019
Programme Priority
4
Overall Priority
Higher
Category
Compliance

Documentation