Report for January 2019

Report Date
January 2019
Achievements to date
  • Project Brief has been approved by the stakeholders

Issues

There are no issues to report at this stage.

Next Steps 
  • Present Project Brief to WIS and Business for approval
  • Project plan revised accordingly in line with RES069 timescales
  • Project Team established
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
There is a dependency upon the delivery of RES069 and confirmation of budget for 2019/2020 needs confirmation to proceed with the remaining upgrades.
Change Status
Time
Moderate
Cost
Moderate
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
There is a dependency upon the delivery of RES069 and confirmation of budget for 2019/2020 needs confirmation to proceed with the remaining upgrades.
Activity
Approved budget
100.0 days
Activity this month
1.8 days
Activity this year
4.9 days
Activity to date
4.9 days
Estimate to complete current year
42.0 days
Estimate to complete future years
58.0 days

Project Info

Project
PURE Upgrades v5.13 to v5.15
Code
RIS007
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Nov-2018
Planning Date
31-Jan-2019
Delivery Date
19-Nov-2019
Close Date
10-Dec-2019
Programme Priority
4
Overall Priority
Higher
Category
Compliance

Documentation