Report for March 2019

Report Date
March 2019
Achievements to date
  • Project is suspended until the completion of RES069

Issues

There are no issues to report at this stage.

Next Steps 
  • Unsuspend project and continue with the delivery of the remaining upgrades
Project Status
RAG Status
Time
BLUE
Cost
AMBER
Scope
BLUE
Overall
AMBER
RAG Commentary
This project has been suspended until RES069 has been completed expected to be restarted in April, however milestones for project are planned into next financial year therefore budget will be required into 19/20 to complete the project. Implications on budget for next financial year will be reviewed when project has been reinstated
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
PMO
Activity
Approved budget
100.0 days
Activity this month
0.0 days
Activity this year
7.0 days
Activity to date
7.0 days
Estimate to complete current year
22.5 days
Estimate to complete future years
66.5 days

Project Info

Project
PURE Upgrades v5.13 to v5.15
Code
RIS007
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Nov-2018
Planning Date
31-Jan-2019
Delivery Date
19-Nov-2019
Close Date
10-Dec-2019
Programme Priority
4
Overall Priority
Higher
Category
Compliance

Documentation