Report for April 2019

Report Date
April 2019

Achievements

Project unsuspended and planning resumed following RES069 completion.

Initial meeting held with Damon Querry.

 

Issues

No major issues

 

Next steps

Project team meeting scheduled 10 May to determine next steps.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
0.8 days
Activity this year
7.8 days
Activity to date
7.8 days
Estimate to complete current year
28.8 days
Estimate to complete future years
66.5 days

Project Info

Project
PURE Upgrades v5.13 to v5.15
Code
RIS007
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Nov-2018
Planning Date
31-Jan-2019
Delivery Date
19-Nov-2019
Close Date
10-Dec-2019
Programme Priority
4
Overall Priority
Higher
Category
Compliance

Documentation