REF2021 Data Requirements Analysis - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 BLUE 103.0 days 89.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Tuesday, 27 November 2018
Planning Date
Wednesday, 27 February 2019
Delivery Date
Thursday, 14 November 2019
Close Date
Thursday, 19 December 2019
Project information
Project Code
RIS008
Programme
Research Information Systems (RIS)
Session
19/20
18/19
Organisational Unit
Library and University Collections
Project Management Office (if relevant)
ISG PMO
Responsibility
Library and University Collections
Project Category
Discretionary
Project Classification
Grow
Funding Source
Digital Transformation
Programme Priority
5
Overall Priority
Normal