Report for July 2019
- Report Date
- July 2019
Achievements in Last Period
- Business requirements document (BRD) signed off by GaSP
- Remaining milestones have been replanned
Issues
- Documents have not been circulated to a wider audience due to waiting on information form Core Systems
- The follow-up meeting with Core Systems team has been delayed due to a Systems meeting through the Finance Transformation Board.
- BA has left the University, While this does not have a significant impact as the BRD is all but signed off, this will involve some additional tasks for the Data Architect. This has been planned in early August.
Next Steps
- Circulate BRD to wider stakeholders for comment
- Hold follow up meeting with Core Systems team
- Create updated Options Appraisal document, circulate to stakeholders
- Move to Closure
- Approved budget
- 84.0 days
- Activity this month
- 11.1 days
- Activity this year
- 69.0 days
- Activity to date
- 69.0 days
- Estimate to complete current year
- 17.0 days
- Estimate to complete future years
- 0.0 days