Report for September 2019

Report Date
September 2019
Achievements in Last Period
  • Prototype development has been progressed
  • Options Paper updated and sent to Applications Director 
  • Remaining milestones re-planned

Issues

  • Documents have not been circulated to a wider audience due to waiting on information form Core Systems
  • Pinning down the requirements for the prototype took much longer than anticipated. This was attributed to consideration given to various edge cases.

Next Steps 

  • Circulate Options Paper to wider audience
  • Move project to closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
REF2021 Data Requirements Analysis
Code
RIS008
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Jacqueline McMahon
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
27-Nov-2018
Planning Date
27-Feb-2019
Delivery Date
14-Nov-2019
Close Date
19-Dec-2019
Programme Priority
5
Overall Priority
Normal
Category
Discretionary