Report for November 2019

Report Date
November 2019

Achievements in Last Period

  • Feedback from REF team received and partially incorporated into Options Paper
  • The final two milestones have again been replanned

Issues

  • There has been a slight delay in finalising the Options Paper due to the Data Analyst and paper author being on planned annual leave.¬†

Next Steps 

  • Complete feedback and circulate Options Paper for sign off to COre and REF Team
  • Draft closure report
  • Closure project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
The delay has had an impact on the implementation project which should have now started. However, the implementation of the proposed solution should be significantly shorter than initially forcast.
Activity
Approved budget
103.0 days
Activity this month
0.8 days
Activity this year
22.0 days
Activity to date
84.0 days
Estimate to complete current year
3.5 days
Estimate to complete future years
0.0 days

Project Info

Project
REF2021 Data Requirements Analysis
Code
RIS008
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Jacqueline McMahon
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
27-Nov-2018
Planning Date
27-Feb-2019
Delivery Date
14-Nov-2019
Close Date
19-Dec-2019
Programme Priority
5
Overall Priority
Normal
Category
Discretionary