Worktribe Upgrade v3.1 - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2020 BLUE 33.0 days 32.3 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Thursday, 18 July 2019
Planning Date
Friday, 16 August 2019
Delivery Date
Thursday, 21 May 2020
Close Date
Friday, 24 July 2020
Project information
Project Code
RIS012
Programme
Research Information Systems (RIS)
Session
19/20
18/19
Organisational Unit
Library and University Collections
Project Management Office (if relevant)
ISG PMO
Responsibility
Library and University Collections
Project Category
Compliance
Project Classification
Run
Funding Source
Core Funded
Programme Priority
4
Overall Priority
Normal
Student Impact
Project deliverables will have no impact on students