Report for April 2020

Report Date
April 2020

Achievements

  • Agreed with business and third party vendors on deployment of SSO changes

Issues

  • SSO changes still not implemented
  • Outstanding milestones to be signed off

Next steps

  • Sign off remaining milestones
  • Implement SSO changes
  • Close project

 

Milestones (to be confirmed)

 

Deliver Delivery of SSO changes 21-May-2020 No
Deliver Delivery sign-off (SSO) 28-May-2020 No
Close Project closure 04-Jun-2020 No

 

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
This project is AMBER because of the outstanding work on implementing the SSO changes. The difficulty has been getting this task resourced - now confirmed with vendors.
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
Yes
Escalated to
Programme Manager & Programme Owner
Change Commentary
Outstanding milestones have been pushed out, and we are awaiting agreement on new dates.
Activity
Approved budget
33.0 days
Activity this month
1.9 days
Activity this year
25.3 days
Activity to date
27.1 days
Estimate to complete current year
3.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Worktribe Upgrade v3.1
Code
RIS012
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
18-Jul-2019
Planning Date
16-Aug-2019
Delivery Date
21-May-2020
Close Date
24-Jul-2020
Programme Priority
4
Overall Priority
Normal
Category
Compliance

Documentation