Report for May 2020

Report Date
May 2020

Achievements

  • SSO changes now deployed in TEST

Issues

  • SSO changes still to be signed off

Next steps

  • Sign off TEST milestones
  • Implement SSO changes in LIVE
  • Close project

 

Milestones (to be confirmed)

 

Deliver Delivery of SSO changes (LIVE) 12-June-2020 No
Deliver Delivery sign-off (SSO) 19-June-2020 No
Close Project closure 26-Jun-2020 No

 

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
This project is AMBER because of the outstanding work on finalising SSO changes.
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
Yes
Escalated to
Programme Manager & Programme Owner
Change Commentary
Final changes have been delayed slightly but within reasonable limits
Activity
Approved budget
33.0 days
Activity this month
0.8 days
Activity this year
26.1 days
Activity to date
27.9 days
Estimate to complete current year
3.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Worktribe Upgrade v3.1
Code
RIS012
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
18-Jul-2019
Planning Date
16-Aug-2019
Delivery Date
21-May-2020
Close Date
24-Jul-2020
Programme Priority
4
Overall Priority
Normal
Category
Compliance

Documentation