Report for August 2019

Report Date
August 2019

Achievements

  • Project brief completed and signed off

Issues

  • None

Next steps

  • Establish work on Shibboleth solution
  • Schedule next stages with business partners and vendor

 

Milestones

 

Build Build complete (DEV) 12-Sep-2019
Accept Integration & Acceptance complete 03-Oct-2019
Deliver Delivery 10-Oct-2019
Deliver Delivery sign-off 22-Oct-2019
Close Project closure 31-Oct-2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
33.0 days
Activity this month
3.1 days
Activity this year
3.1 days
Activity to date
4.9 days
Estimate to complete current year
26.8 days
Estimate to complete future years
0.0 days

Project Info

Project
Worktribe Upgrade v3.1
Code
RIS012
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
18-Jul-2019
Planning Date
16-Aug-2019
Delivery Date
21-May-2020
Close Date
24-Jul-2020
Programme Priority
4
Overall Priority
Normal
Category
Compliance

Documentation