Report for July 2020
- Report Date
- July 2020
Achievements this Period
- Liaise with project team regarding impact of GENLIVE upgrade and RIS012 SSO release.
- Upgrade of TEST environment to v2020.1 and test cycle completed.
- Scheduled update of LIVE in step with RIS012.
- Upgrade of LIVE from v3.1 to v2020.1. Test and sign off the LIVE upgrade.
- Closure report raised at WIS of 31/07/2020.
- Project approved for closure.
Issues
- Project scope expanded to move to v2020.1. API interfaces work to be addressed as a new project to transition interfaces from SFTP to API's by 31/03/2021.
- Refresh of GENDEV shouldn't impact project but needs to be monitored.
Next Steps
- Approved budget
- 30.0 days
- Activity this month
- 4.8 days
- Activity this year
- 15.8 days
- Activity to date
- 15.8 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days