Worktribe Upgrade v2020.7 - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2020 BLUE 11.0 days 10.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Friday, 11 September 2020
Planning Date
Friday, 2 October 2020
Delivery Date
Monday, 30 November 2020
Close Date
Friday, 11 December 2020
Project information
Project Code
RIS017
Programme
Research Information Systems (RIS)
Session
20/21
Organisational Unit
Library and University Collections
Project Management Office (if relevant)
ISG PMO
Responsibility
Library and University Collections
Project Category
Compliance
Project Classification
Run
Project Type
Implementation
Project Size
Small
Project Complexity
Simple
Alignment to Strategy 2030 and Adaptation & Renewal Team (ART)
Research
Funding Source
Core
Overall Priority
Highest