Closure Report

Project Summary

Worktribe, the company responsible for producing the University’s pre-award/post-award research administration management system, releases 2 major versions of the application per year.

This project was initiated so the University's Worktribe application could be kept with one major release behind Worktribe’s schedule. The upgrade to each of the environments is carried out by Worktribe, while IS Apps involvement is limited to a review of the changes in the release notes, assessing compatibility and testing the upgrades after they are completed.

 

The project's timeline of events are as follows:
Monday, 7 November 2022 Planning completed and signed off by project team and Apps Review
Monday, 31 October 2022

v2022.7 DEV Upgrade completed successfully

Thursday, 24 November 2022 UAT completed for v2022.7
Wednesday, 7 December 2022 V2022.7 successfully deployed to TEST and LIVE (Note that Worktribe deploy to TEST and LIVE at the same time. UAT is completed on DEV)
Project was now on hold until the next release of v2023.1 which was due at the beginning of February 2023.
Industrial action during February meant that the upgrade of v2023.1 to DEV was delayed until March
Wednesday, 8 March 2023 v2023.1 DEV Upgrade completed successfully
Monday, 3 April 2023 UAT completed for v2023.1
Thursday, 6 April 2023 V2023.1 successfully deployed to TEST and LIVE
April Project Closure

 

Scope

The scope of this project is to upgrade the University’s installation of Worktribe to v 2022.7 and v 2023.1. This has been successfully achieved. 

There were no scope changes throughout the project.

Objectives and Deliverables

No

Description

MoSCoW

Owner

Achieved? 

O1

To apply the Worktribe v2022.7 upgrade to all necessary environments (DEV, TEST and LIVE)         

 

 

D1

Upgrades of Worktribe to v2022.7 in DEV, TEST and LIVE environments at the University of Edinburgh

Must                         

Worktribe  

Yes

 

O2

To fully test the version upgrade and how it is applied across our environments                                    

 

 

Achieved? 

D2   

Full tests of business processes adopted by the University on Worktribe application

Must                      

Project team   

Yes

D3

Testing of the interfaces presenting data to Worktribe from P&M, HR, and IDM

Must

Project team

Yes

D4

Testing of the outgoing interfaces between P&M and Worktribe 

Must

Project team

Yes

D5

Tests of the external reporting solution (and the Worktribe BI Extract) 

Must

Project team

Yes

D6

Testing of additional and/or enhanced functionality to the system 

Must

Project team

Yes

 

O3 

To update any relevant user support pages in our Wiki and related guidance documentation          

 

 

Achieved?

D7

Updated versions of support materials 

Must                      

Project team   

Yes

 

O4

To apply the Worktribe v2023.1 upgrade to all necessary environments (DEV, TEST and LIVE)        

 

 

Achieved?

D8 

Upgrades of Worktribe to v2023.1 in DEV, TEST and LIVE environments at the University of Edinburgh

Must                       

Worktribe   

Yes

 

O5

To fully test the version upgrade and how it is applied across our environments                                   

 

 

Achieved?

D9 

Full tests of business processes adopted by the University on Worktribe application

Must                       

Project team   

Yes

D10

Testing of the interfaces presenting data to Worktribe from P&M, HR, and IDM

Must

Project team

Yes

D11

Testing of the outgoing interfaces between P&M and Worktribe 

Must

Project team

Yes

D12

Tests of the external reporting solution (and the Worktribe BI Extract) 

Must

Project team

Yes

D13 

Testing of additional and/or enhanced functionality to the system 

Must

Project team

Yes

 

O6

To update any relevant user support pages in our Wiki and related guidance documentation        

 

 

Achieved? 

D14  

Updated versions of support materials 

Must

                       Project team   

Yes

 

Analysis of Resource Usage:

Staff Usage Estimate: 30 days

Staff Usage Actual: 25 days

Resource Variance: -20%

 

Explanation for Variance

The initial estimate at the start of the project was for 30 days. (15 days for each upgrade).

After the delivery of the first upgrade to V2022.7 in December, a budget review was carried out in January. This indicated that 5 days could be returned to the programme, now giving the project 25 days to complete. This was down to the minimal issues encountered during the first upgrade, and the release notes in the second upgrade did not indicate any major updates in that release. 

Key Learning Points

Issue / What went well Key Learning Point

UAT is carried out in DEV. Issue noted that there were RMAS database errors.

We need IS APPS involved for the application and interface checks on DEV.

There had been a data refresh from LIVE into DEV and TEST. The API DEV user is not in LIVE so was not copied over. 

Checks needed to make sure the database users are present and correct in DEV if a data refresh has taken place. 

Worktribe were not updating calls to say they had completed the upgrades. This left the project team wondering if the upgrade had been missed, had issues or had finished.

This has been raised with Worktribe. They noted that you can see what version UoE is on by logging into the Worktribe tracker and hovering the mouse pointer over the Worktribe logo.  However they will update calls in the future.

 

Worktribe upgrade TEST and LIVE on the same day. This generally doesn't affect UAT as it is done on DEV A suggestion was made by Production to carry out basic checks immediately after TEST has been upgraded so we can get back to Worktribe if there are any major issues before LIVE is completed. 
Dashboard checks required.

We need ERO colleagues to check the reports on the ERO Intel Dashboard to ensure that the reports load and are not altered.

 

Outstanding Issues

There are no outstanding issues. 

Project Info

Project
Worktribe Upgrades v2022.7 and v2023.1
Code
RIS024
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
22-Sep-2022
Planning Date
20-Oct-2022
Delivery Date
23-Mar-2023
Close Date
27-Apr-2023
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation

Close